Town Issues Update on Current Water Line Project in Winsted

6

Department of Public Works Project Manager Bart Clark has provided an update on the status of the water line project currently underway in Town.

Ludlow Construction has been working on Holabird Avenue,  having installed temporary water service pipes and valves to allow the  water main to be isolated there.  The contractor has been waiting for  the delivery of the needed pipe and expects delivery of the necessary  pipe by the end of the week.

Today, May, 19th, Ludlow Construction  has begun installing temporary service lines in Center Street, Case  Avenue, Greenwoods Avenue, and Thibault Avenue.  They will be working in  this area through the end of the week.  If the pipe is delivered as  expected,  they will stop working in this area and go back to working on  Holabird Avenue.

The public is advised that temporary water lines  narrow the roadway slightly so parking will be a little more  difficult.  Residents and patrons of the downtown businesses are advised  that they can use the Elm Street Fire House parking lot in order to  park out of the construction area. 

The patience of the public is very much appreciated as these infrastructure improvements are completed.

Original source can be found here.

ORGANIZATIONS IN THIS STORY

!RECEIVE ALERTS

The next time we write about any of these orgs, we’ll email you a link to the story. You may edit your settings or unsubscribe at any time.
Sign-up

DONATE

Help support the Metric Media Foundation's mission to restore community based news.
Donate

MORE NEWS